Renewable Energy Solutions

CARER management team has provided successful consulting services in the field of renewable energy sources throughout Kazakhstan. In everything we do, our goal is to minimize the risk for our customers, maximize project efficiency and profitability, and guarantee their long-term success.

dfdfdf
BURNOYE SPP (100 MW)

Location: B. Momyshuly village, Zhambyl  region, Kazakhstan;

Status: Commissioned;

Client: United Green (UK).

Role of CARER team:

  • Development of project;
  • Financial structuring;
  • Obtainment of debt financing from EBRD and  Clean Technology Fund;
  • Obtainment of custom duty exemptions;
  • Supervision of construction works (AC & DC);
  • Grid connection services for 220 kV;
  • Commissioning of project.
ZADARYA SPP (14 MW)

Location: Arys village, Turkestan region,  Kazakhstan;

Status: Planned to be commissioned in November  2019;

Client: Urbasolar SAS (France).

Role of CARER team:

  • Development of project;
  • General contractor for construction of AC  (substation and grid connection to 35 kV);
  • Owner's engineer service (all stages of project implementation including commissioning);
  • Obtainment of debt financing from EBRD and  Clean Technology Fund;
  • Obtainment of custom duty exemptions;
  • Tax advisory.
KUYANOVKA SPP (7 MW)

Location: Kuyanovka village, Sumy region,Ukraine;

Status: Planned to be commissioned in November 2019;

Client: Georgian Industrial Group (Georgia).

Role of CARER team:

  • Main contractor for construction of DC side;
  • Commissioning of project (DC).
GULSHAT SPP (40 MW)

Location: Gulshat village, Karaganda region,  Kazakhstan;

Status: Commissioned in February 2019;

Client: Risen Energy (China).

Role of CARER team:

Development of project;

General contractor for construction of DC  and AC (110 kV) sides of SPP;

Commissioning of SPP;

O&M for 5 years;

Obtainment of custom duty exemptions;

Tax advisory.

CHULAKKURGAN SPP (50 MW)

Location: Chulakkurgan village, Turkestan region, Kazakhstan;

Status: Planned to be commissioned in December 2019;

Client: Risen Energy (China).

Role of CARER team:

  • General contractor for construction of DC and AC sides;
  • Reconstruction of grid lines and substation;
  • Grid connection to 110 kV
  • Commisioning of SPP.
MISTRAL SPP (50 MW), KAPSHAGAY SPP (100 MW), ZHANGIS SPP (30 MW)

Location: Kazakhstan;

Status: Mistral SPP - construction; Kapshagay SPP - commissioned; Zhangis SPP - commissioned

Client: Universal Energy (China).

Role of CARER team:

  • Tax advisory;
  • Obtainment of custom duty exemptions;
  • Independent evaluation of installation works of equipment in AC side;
  • Assistance in commisioning.